Create a network diagram and a Gantt chart for the project tasks.

Create a network diagram and a Gantt chart for the project tasks.
What is the planned duration for the testing project?
What is the critical path for the testing project?
For each task NOT on the critical path, calculate the amount of slack available.
If the user testing of the user interface takes 15 days, what will the impact be on the project duration?

× How can I help you?