Create a testing plan
Once the testing plan is ready, your team can:

Test the user interfaces
Test the database
Test the network
Write the documentation first draft
When the user interface tests are complete, you can:

Perform user testing—enlist some users to test the user interface
When the database and network testing are complete, you can:

Perform integration testing—network with the database
When the user testing of the user interface and the database testing are complete, you can:

Perform integration testing—database, network, and user interface
When all integration testing and user testing are complete, you can:

Perform system testing
Then you can:

Review and revise documentation
After all other tasks are complete, you can:

Obtain management approval
Duration estimates for the tasks:

a.3 days

b.10 days

c.6 days

d.7 days

e.20 days

f.5 days

g.3 days

h.2 days

i.8 days

j.4 days

k.5 days